JE Dunn was the construction manager for the Shamrock Zone renovation and expansion at the Kansas State University Bill Snyder Football Stadium. This new addition required the demolition of existing athletic offices that were directly attached to the Bramlage Coliseum. After the demolition of the offices, the new south end zone addition tied the north Bramlage Coliseum concourse to the new Shamrock Zone allowing both basketball and football fans access to a Premium Club with direct access to stadium club and loge seating. This multi-phased project was completed by the start of the 2021 football season.
The project began in January 2019 just before COVID-19 and construction work took place during the 2020 Football Season with no loss of existing seats. Our construction team completed all primary steel to ensure safe ingress and egress during all football games. The complete building was turned over in July 2021. The football offices were turned over a month early to allow for proper move-in time prior to the start of the 2021 Football Season.