JE Dunn recently completed a 568,476 SF, two-story, 58MW data center for Digital Realty - the first data center on a 41-acre site.
The team was originally awarded the core and shell and four of the eight suites. After success with the first “phase” of work, we were awarded an additional four suites, totaling eight suites of base build and tenant fit up. The tenant fit-up includes busway, hot aisle containment, fiber pathways, fiber, labeling and testing.
The build is Block Redundant 4-to-make-3 N+1 system with static transfer switches and A/B busway distribution. It includes two 35kV loops, the 220/240 loop is 9MVA and the 260/280 loop is 14MVA. The systems were built with prefabricated Skidded power modules to provide a faster schedule and startup. Each power skid module contains (2) 1000KVA UPS modules in parallel to provide a total of two MVA per power skid module.
A true plug-and-play delivery for tenant rack installation for 58MW of capacity in 24 months.