LightEdge

Data Center and Facility Expansions

For the past decade, JE Dunn has provided construction services for Cavern Technologies – recently acquired by LightEdge – located in the Meritex caves in Lenexa, Kansas. Projects include both the initial construction of data center space and facility expansions.

In 2016, we completed Phase 4A Day Two Space including 16,000 SF of whitespace with over 30 feet raised access floor space, contained in a hard-shell structure of masonry walls and 60 feet of solid rock above. A modern and spacious washroom, fully stocked break area, and several meeting spaces are also part of this facility.

In 2019, we completed Phase 4B, a build-out of four large tenant rooms totaling 28,203 SF of white space to the co-location data space.

Security is a top priority, and all access points are controlled with 24/7 client access through manned and key card control. The facility is equipped with a state-of-the-art Network Operations Center (NOC) with 24/7 manned monitoring.

Location
Lenexa, Kansas
Client
LightEdge Solutions
Architect
Bell-Knott and Associates
Completion Date
July 2019
6
Expansions Since 2012
125
Feet Below Ground

Related Content

Thought Leadership
Advanced Industries Industrial & Manufacturing Mission Critical
JE Dunn Announces Its Newly Formed Advanced Facilities Group
Paul Neidlein
Advanced Facilities Group President
June 2024
Projects
Advanced Industries Mission Critical
Santa Clara
Confidential Client Data Center Project
Confidential Client
Santa Clara, CA
Publication
Mission Critical
The Look Ahead: Consumer Spending, 2023 Outlook, and Mission Critical Spotlight
February 2023
Projects
Mission Critical
Portland
Digital Realty
Data Center
Digital Realty
Portland, Oregon
In The News
Mission Critical
Successful Setup: The Advantage of Medium-voltage Cabling
Mike Fernholz
Senior Engineering Services Manager
October 2021
Prefabrication & Manufacturing
In The News
Mission Critical
Maximizing Modular Construction to Increase Speed to Market
Marcus Walker
Engineering Services Manager
October 2020
Prefabrication & Manufacturing
In The News
Mission Critical
Down to the Last Detail: Using Advanced Work Packaging to Increase Predictability in Planning
June 2020
Projects
Mission Critical
Portland
Idaho National Laboratory
C3 Data Centers
Idaho National Laboratory
Idaho Falls, Idaho
Projects
Mission Critical
Dallas
Stream Data Center
DFW VII
Stream Data Centers
Garland, TX
Mission Critical
Omaha
John Hoodjer of JE Dunn Construction Receives National Recognition
John Hoodjer
Vice President
Group Manager
No data was found
No data was found