je dunn construction master logo
Preconstruction
Design
Case Study
Sports & Recreation
Wichita

Surging Ahead in Ballpark Construction

Bringing baseball to Wichita, Kan., required a non-traditional delivery method to condense the schedule to complete construction in time for Opening Day.

The ask: design and build a minor league baseball park from concept to completion in 15 months. The challenge: typical ballpark construction require a year longer than that, with 8-10 months for design alone. Prior to the pandemic, the goal was to open prior to the Wichita Wind Surgeโ€™s inaugural season, thus the compressed timeline. To meet the aggressive goalsโ€”as well as opening dayโ€”the team and owner worked in tandem to execute a non-traditional delivery method that shaved off a significant time from comparable projects.

Implementing a New Approach
To implement the forward-thinking method, the team employed a โ€œjust-in timeโ€ delivery for materials as well as with design, which was a new approach for the architects. By developing a design schedule that allowed the design team to focus their efforts on the areas that were to be constructed next, we were able to coordinate a process that closely aligned design with construction, resulting in more efficient use of everyoneโ€™s time. For example, design of the 3rd baseline was being completed with materials being procured while design was still being completed along the 1st baseline.

In addition to a unique approach for the design-build schedule, the team initially agreed on a more phased approach for the structural systems. Collaboration between the Design Build Team and steel trade partner allowed us to make critical design decisions based on aesthetics, availability of material and pricing within hours as opposed to weeks. This approach provided the engineers with information needed to design the foundations needed immediately to get the seating bowl constructed while steel was being fabricated. The key to the success of the project was making informed decisions quickly for the next phase of design to be completed just in time.

Ground Water Challenges
Because the ballpark was located along a river, the project required a specially designed system of underground wells to address the presence of ground water in the area. The system specifically keeps ground water from rising to a level that would enter the subgrade and jeopardize the integrity of the playing field. These dewatering wells complemented the underground field drainage system. While not related to any typical fan experience, the ground water wells are one of the most important aspects of the ballpark. Using historical geological documents, we engaged a hydrologist to analyze and design the wells to ensure groundwater fluctuations donโ€™t compromise the playing field.ย  Similar to other aspects of design, the hydrologist worked closely with the project team to provide the most time sensitive and cost-effective design.

All About the Fans
Keeping the fan experience in mind, the team put themselves in spectatorsโ€™ shoes when designing and constructing the seating bowl to allow unobstructed sight lines. To create a quality concrete seating structure, a modular form system on wheels was used. This system had the ability to set the riser dimensions for each tread individually. Once the riser depth was set, concrete could be placed. Once cured, the system could be released and rolled to the next seating section creating a consistent riser height at each tread throughout the seating bowl.

As important as it was to have unobstructed sight lines, spectator safety was also top of mind. The glass used in the amenity spaces had to withstand the damage caused by a foul ball while preventing injury to spectators in addition to remaining clear for visibility reasons. To overcome this challenge, our team utilized two layers of ยผ” laminated glass on the outboard side, to prevent shards of glass from injuring spectators. During the construction process, the glass panels were installed at the club and despite the strength being correct, the laminated glass created vertical waves which caused visual distortion while looking out at the playing field. โ€œAfter researching, we discovered the annealing (strengthening) process of glass could be accomplished in multiple ways.ย  In order to ensure the viewing quality met major league standards, the glass at the club was removed and replaced with 3/8โ€ tempered glass that provided much clearer, unobstructed visibility to the playing surface while not compromising safety,โ€ said Vice President Scott Sherry.

From permitting to approvals to extreme coordination, the success of the Wichita ballpark relied on buy-in from all parties, including the ownership group. โ€œIn addition to the challenges of the incredibly aggressive schedule, toward the end of the project we were confronted with the disruptive effects of the Coronavirus โ€ฆ yet the stadium was constructed on time and on budget,โ€ said Jordan Kobritz, partner/senior advisor for Wichita Wind Surge. A big step in the revitalization of the neighborhood, the only thing left to do is play ball.

David Young
Vice President
Project Executive

related headlines

Projects
Sports & Recreation
Kansas City
American Royal Association
New American Royal Complex
American Royal Association
Kansas City, KS
Projects
Sports & Recreation
Dallas
Southern Methodist University
Gerald J. Ford Stadium Garry Weber End Zone Complex
Southern Methodist University
Dallas, TX
Projects
Sports & Recreation
Dallas
Baylor University
Football Operations Building
Baylor University
Waco, Texas
Projects
Sports & Recreation
Atlanta Kansas City
Classic Center Arena
Classic Center Authority/Unified Government of Athens Clarke County
Athens, GA
Projects
Sports & Recreation
Kansas City
KC Current Stadium
KC Current
Kansas City, Missouri
Projects
Sports & Recreation
Kansas City
American Royal Association
New American Royal Complex
American Royal Association
Kansas City, KS
Projects
Sports & Recreation
Dallas
Southern Methodist University
Gerald J. Ford Stadium Garry Weber End Zone Complex
Southern Methodist University
Dallas, TX
Projects
Sports & Recreation
Dallas
Baylor University
Football Operations Building
Baylor University
Waco, Texas
Projects
Sports & Recreation
Atlanta Kansas City
Classic Center Arena
Classic Center Authority/Unified Government of Athens Clarke County
Athens, GA
Projects
Sports & Recreation
Kansas City
KC Current Stadium
KC Current
Kansas City, Missouri
Projects
Sports & Recreation
Kansas City
Kansas State University
Volleyball & Olympic Training Facility
Kansas State University
Manhattan, KS
Publication
Sports & Recreation
The Look Ahead: ESG in Construction and Sports Spotlight
May 2023
Women in Construction Week
Campaigns
Sports & Recreation
Kansas City
KC Current Stadium at Berkley Riverfront Park
March 2023
Projects
Healthcare
Wichita
Wesley Medical Center
Pediatric and Exterior Facade Renovations
HCA Healthcare
Wichita, Kansas
Projects
Sports & Recreation
Kansas City
Kansas State University Bill Snyder Football Stadium
Shamrock Zone Expansion
Kansas State University
Manhattan, Kansas
Projects
Sports & Recreation
Atlanta
Georgia Tech Baseball
Russ Chandler Stadium Renovation
Georgia Institute of Technology
Atlanta, GA
Projects
Historical Preservation Sports & Recreation
Kansas City
Kirk Family YMCA
YMCA of Greater Kansas City
Kansas City, Missouri
Projects
Education Sports & Recreation
Charleston
Charleston County School District
High School Stadium
Charleston County School District
Charleston, South Carolina
Projects
Education Sports & Recreation
Colorado Springs
William J. Hybl
Sports Medicine and Performance Center
University of Colorado Colorado Springs
Colorado Springs, Colorado
Projects
Sports & Recreation
Wichita
Wichita Riverfront
Minor League Baseball Stadium
City of Wichita
Wichita, KS
David Young
Vice President
Project Executive
No data was found