Confidential Semiconductor Tool Manufacturing Company

RGL Phase 2 Cleanroom/Subfab

Project Highlights

  • 50,000-square-foot interior buildout including a SF ISO 6 Class 100 cleanroom to expand the existing semiconductor facilities.
  • Coordination and collaboration with the client’s engineering and operations teams were an essential aspect associated to the success of the project.
  • Part of our strategy was to focus on ensuring the section of the fab that was completed first, was the section that was receiving the first tool.
  • Completed with ZERO interruptions.

 

 

 