This project included a 50,000-square-foot elevated, multi-level cleanroom link that connected three existing fabrication facilities together.
JE Dunn worked closely with the facility system owners to coordinate construction activities and keep their highly sensitive microchip fabrication facilities operational 24/7. All new utilities were successfully installed with zero impacts.
Prefabrication equated to labor savings of $1.4M and 24 weeks in time savings.
The team developed and proposed 103 value options during the programming/design phase. JE Dunn proposed $36M in savings and the client accepted $23M. Equipment procurement saved $3.5M through direct purchasing and introduction of alternate suppliers.