To retain the predictability and accuracy clients need, it’s the behind-the-scenes, up-front work and collaboration that can have a substantial impact on achieving project goals. While it’s not always front and center, leveraging procurement is a crucial piece of not only getting projects off the ground, but also in setting each one up for success.
The importance of swift decisions and sound processes—in addition to remaining adaptable—are essential in a time when trade partners cannot guarantee pricing over 90 days and lead times have swelled in some cases to 6 months. To combat the issues and avoid delays that could impact the overall project schedule, the team took a proactive approach to identify items with long lead times, allowing all parties to plan accordingly within the project schedule.
For this project, below are all the items we identified to secure preauthorization from the owner to begin procurement of these long lead items ahead of the main contract execution. Once the trades were cut loose on early procurement, we worked closely with the reps to get their submittals in.
In addition to identifying potential delays and prioritizing those items, trade partner buy-in and early submittals are critical to starting construction on time. By identifying long lead items that are critical to construction, we got the ball rolling on submittal development and submittal reviews and expedited the release for fabrication ASAP. We were experiencing a factory workforce shortage on our air handling units, which caused a one-month slip. If they weren’t in the fabrication que, this could’ve been a substantial delay.
Recent delays and uncertainty caused by the current landscape have forced teams to get creative in their processes and adjust them to account for potential issues. Improvements in the procurement process at TMC Rincon include:
In short-term, the goal was to avoid potential delays caused by interruptions in the supply chain—but what the team did not realize at the time is just how impactful those decisions would end up being in the long-term due to (still) increasing escalation and inflation. We were able to lock in long-lead equipment orders into the factories to avoid longer disruptions and save costs. Our AHUs slipped an entire month due to a manpower shortage at the factory; if we had not gotten a preauthorization, our AHU would have slipped significantly and jeopardized the project schedule.
While project teams have adjusted to the changing procurement issues, the fact remains that no one can predict how long these challenges will persist. Though it’s been difficult at times, the benefits of evolving to tackle these issues will only improve future processes and create more efficiencies going forward. “Having an efficient, proven procurement process in place is beneficial to everyone involved in each project,” said Procurement Director Jason Banks. “In addition to helping head off delays in the field and keeping work moving the pace required by the schedule, it also creates a team atmosphere from top to bottom to increase transparency and engagement across the board.”